Hoosier Line Solar
180 MW generation in White, IN · In queue since September 2019 · Proposed COD September 2027
180 MW
Capacity
1
Components
Solar
6y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
8 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-15
The Hoosier Line Solar project is a proposed 180 MW solar generation facility in White County, Indiana. The project, under development in the PJM Interconnection queue as entry PJM-AF1-207, was initially entered into the queue on September 27, 2019, with a proposed commercial operation date of September 15, 2027. The interconnection utility is AEP, and the project's point of interconnection is the Reynolds-Olive #1 345 kV line. Its interconnection status is currently in the Facility Study phase.
The Hoosier Line Solar project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Reynolds-Olive #1 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hoosier Line Solar