Cottontail Solar 7
35 MW generation in Columbia, PA · In queue since September 2019 · Proposed COD November 2028
35 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2028-11-30
Cottontail Solar 7 is a proposed 35 MW solar generation project located in Columbia County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF1-226, with a queue entry date of September 28, 2019. The proposed commercial operation date is November 30, 2028. The interconnecting utility is PPL. The project's interconnection agreement has been executed, but its current status is listed as suspended.
The development project consists of 35 MW of solar photovoltaic generation. It is interconnected to the grid at the Bowmans Mill-Scott 69 kV point of interconnection.
Generated from interconnection queue and public data sources
State
PA
County
Columbia
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Bowmans Mill-Scott 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM