Tymochtee Solar
120 MW generation in Wyandot, OH · In queue since September 2019 · Proposed COD August 2027
120 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-08-31
The Tymochtee Solar project is a proposed 120 MW solar generation facility located in Wyandot County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF1-229, with a queue entry date of September 27, 2019, and a proposed commercial operation date of August 31, 2027. The interconnection agreement has been executed. The point of interconnection is the Galion-South Berwick 345 kV line.
The project is being developed within the AEP utility territory and has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
OH
County
Wyandot
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Galion-South Berwick 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tymochtee Solar