PJM-AF1-238
50 MW storage in Cumberland, NJ · In queue since September 2019 · Proposed COD May 2023
50 MW
Capacity
1
Components
Battery
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 8m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-31
The proposed energy storage project PJM-AF1-238 is a 50 MW battery development in Cumberland County, New Jersey. Interconnection is with the PJM Interconnection queue, with an entry date of September 28, 2019. The proposed commercial operation date is May 31, 2023. The project's interconnection status is currently in the System Impact Study phase.
The project, which is being developed within the Atlantic Electric Company (AEC) service area, consists entirely of battery storage. The point of interconnection is the Sherman Ave - West Vineland 69 kV line. The project has appeared in recent news coverage regarding energy storage projects in the PJM region.
Generated from interconnection queue and public data sources
State
NJ
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Sherman Ave - West Vineland 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- VINELAND13.8 KV CTYVINEL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF1-238