30 MW storage in Cumberland, NJ · In queue since September 2019 · Proposed COD June 2028
30 MW
Capacity
1
Components
Battery
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The South Orchard project is a proposed 30 MW battery storage development in Cumberland County, New Jersey. The project is located within the PJM Interconnection region and is listed in the PJM queue as entry AF1-239, filed on September 28, 2019. The proposed commercial operation date is June 1, 2028.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Sherman Ave - West Vineland 69 kV line. The project is being managed within the PJM queue.
Generated from interconnection queue and public data sources
State
NJ
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Sherman Ave - West Vineland 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- VINELAND13.8 KV CTYVINEL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.