PJM-AF1-240
15.75 MW generation in Armstrong, PA · In queue since September 2019 · Proposed COD July 2022
15.75 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
2y 10m
Schedule
47 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-07-01
PJM-AF1-240 is a proposed solar generation project located in Armstrong County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 15.75 MW, consists entirely of solar photovoltaic generation. The queue entry date for PJM-AF1-240 is September 30, 2019, with a proposed commercial operation date of July 1, 2022. The project's interconnection status is currently in the System Impact Study phase. The interconnecting utility is PENELEC, and the point of interconnection is the Timblin 34.5 kV substation.
The development project is listed in the PJM interconnection queue. No developer is specified in the queue data. There is no indication of an existing operating plant linked to this project, nor is there mention of any recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Armstrong
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Timblin 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF1-240