Hudson Energy Storage Facility
200 MW storage in Hudson, NJ · In queue since September 2019 · Proposed COD December 2028
200 MW
Capacity
1
Components
Battery
6y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-12-01
The proposed Hudson Energy Storage Facility is a 200 MW battery storage project located in Hudson County, New Jersey. The project, developed by PSEG, is interconnected within the PJM Interconnection queue under queue ID PJM-AF1-245. It entered the queue on September 30, 2019, and has a proposed commercial operation date of December 1, 2028. The project's interconnection agreement has been executed.
The Hudson Energy Storage Facility development has been the subject of recent news coverage, with articles focusing on deals and regulatory aspects.
Generated from interconnection queue and public data sources
State
NJ
County
Hudson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
—
Point of Interconnection
Hudson 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- Central Hudson Beacon Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hudson Energy Storage Facility