FR-Williamsport
20 MW generation in Franklin, PA · In queue since September 2019 · Proposed COD December 2025
20 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
6y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The FR-Williamsport project is a proposed 20 MW solar generation project located in Franklin County, Pennsylvania. The project is in the PJM interconnection queue as entry AF1-254, with a queue entry date of September 30, 2019. The proposed commercial operation date is December 31, 2025.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Milnor-Huyetts 34.5 kV line. The utility is listed as APS. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
PA
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Milnor-Huyetts 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about FR-Williamsport