Hawthorn Solar
83 MW generation in Delaware, IN · In queue since September 2019 · Proposed COD December 2028
83 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-31
Hawthorn Solar is a proposed 83 MW solar generation project located in Delaware County, Indiana. The project, developed under the queue ID PJM-AF1-268, is in the PJM interconnection queue with an entry date of September 30, 2019. The proposed commercial operation date is December 31, 2028, and the interconnection agreement has been executed.
The project is interconnected to the Desoto-Jay 138 kV point of interconnection and has been the subject of recent news coverage related to industry and regulatory matters.
Generated from interconnection queue and public data sources
State
IN
County
Delaware
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Desoto-Jay 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26