G Morris Solar
17 MW generation in Dauphin, PA · In queue since September 2019 · Proposed COD April 2026
17 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-04-15
The G Morris Solar project is a proposed 17 MW solar generation project located in Dauphin County, Pennsylvania. The project is interconnected within the PJM Interconnection queue as project number PJM-AF1-271A, having entered the queue on September 27, 2019. The proposed commercial operation date is April 15, 2026, and the project has an Interconnection Agreement (IA) executed.
The project is within the PPL utility territory. As of the latest data, the project's status within the interconnection queue is listed as suspended. The point of interconnection (POI) is the Gratz 69 kV substation.
Generated from interconnection queue and public data sources
State
PA
County
Dauphin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Gratz 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- Gratz Substation