Hoodlebug Solar Energy Center
110 MW generation in Indiana, PA · In queue since October 2019 · Proposed COD August 2027
110 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-08-31
The Hoodlebug Solar Energy Center is a proposed 110 MW solar generation project located in Indiana County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF1-272, with a queue entry date of October 1, 2019, and a proposed commercial operation date of August 31, 2027. The interconnection agreement for the project has been executed.
The proposed project, which will interconnect to the Lucerne 115 kV point of interconnection, is located within the PENELEC utility territory.
Generated from interconnection queue and public data sources
State
PA
County
Indiana
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Lucerne 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LUCERNE 115 KV NO2 TX
- POI Substation
- Lucerne Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hoodlebug Solar Energy Center