Project PJM-AF1-280 — Project Summary

Queue ID
PJM-AF1-280
Capacity
200 MW
Technology
Solar
Status
active
Location
Lee, IL
Region
PJM
Developer
IA Status
System Impact Study

PJM-AF1-280

PJM-AF1-280BetaActiveSolarPJMLBNL

200 MW generation in Lee, IL · In queue since September 2019 · Proposed COD December 2022

200 MW

Capacity

1

Components

Solar

6y 8m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection

Total Duration

3y 3m

Schedule

42 months past proposed COD

Impact Study25%
Queue EntrySep 10, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

About

PJM-AF1-280 is a proposed 200 MW solar generation project located in Lee County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 10, 2019. Its proposed commercial operation date is December 1, 2022.

Currently, the project's interconnection status is listed as "System Impact Study." The point of interconnection is the Nelson-Lee County area. The interconnecting utility is ComEd.

Generated from interconnection queue and public data sources

Project Details

State

IL

County

Lee

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

ComEd

Entity

PJM

Service Type

Point of Interconnection

Nelson-Lee County

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
N ILLINOIS HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.