Nuthatch Solar 5
100 MW generation in Highland, OH · In queue since September 2019 · Proposed COD May 2030
100 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2030
Total Duration
10y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2030-05-01
Nuthatch Solar 5 is a proposed 100 MW solar generation project located in Highland County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF1-282, with a queue entry date of September 30, 2019. The proposed commercial operation date is May 1, 2030.
The interconnection agreement for Nuthatch Solar 5 has been executed. The project is interconnected to the grid at the Stuart-Clinton 345 kV point of interconnection. Recent news coverage has discussed this development project.
Generated from interconnection queue and public data sources
State
OH
County
Highland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Stuart-Clinton 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Nuthatch Solar 5