Chester Solar Technology Park
20 MW generation in Chesterfield, VA · In queue since September 2019 · Proposed COD June 2027
20 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
The Chester Solar Technology Park is a proposed 20 MW solar generation project located in Chesterfield County, Virginia. The project is being developed within the PJM Interconnection region and is connected to the Tyler 34.5 kV point of interconnection.
The project, identified as PJM-AF1-291 in the PJM queue, entered the queue on September 30, 2019, and has a proposed commercial operation date of June 30, 2027. Its interconnection status is currently in the System Impact Study phase. The utility involved is Dominion. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Chesterfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Tyler 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Chester Solar Technology Park