Jarratt Solar
14.9 MW generation in Greensville, VA · In queue since September 2019 · Proposed COD August 2027
14.9 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-29
The Jarratt Solar project is a proposed 14.9 MW solar generation facility located in Greensville County, Virginia. The project is listed in the PJM interconnection queue as entry AF1-292, with a queue entry date of September 30, 2019. Dominion is the interconnecting utility.
The proposed commercial operation date for Jarratt Solar is August 29, 2027. The project's interconnection status is currently in the System Impact Study phase. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
VA
County
Greensville
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Fields 34.5kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Jarratt Solar