PJM-AF1-294
41 MW generation in Amelia, VA · In queue since September 2019 · Proposed COD December 2022
41 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3y 3m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
PJM-AF1-294 is a proposed solar generation project with a total capacity of 41 MW, located in Amelia County, Virginia. The project is in the PJM interconnection queue, having entered the queue on September 30, 2019. Dominion is the interconnecting utility. The proposed commercial operation date is December 1, 2022.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Jetersville-Ponton 115 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Amelia
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Jetersville-Ponton 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF1-294