PJM-AF1-296
212.1 MW generation in Whiteside, IL · In queue since September 2019 · Proposed COD September 2022
212.1 MW
Capacity
1
Components
Wind
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3 years
Schedule
44 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-09-15
PJM-AF1-296 is a proposed wind generation project with a total capacity of 212.1 MW. The project is located in Whiteside County, Illinois, within the ComEd service area and the PJM Interconnection region. The project entered the PJM queue on September 30, 2019, and has a proposed commercial operation date of September 15, 2022.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is at the Garden Plain 138 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Whiteside
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Garden Plain 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.