PJM-AF1-302
42 MW generation in Jefferson, PA · In queue since September 2019 · Proposed COD December 2027
42 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-31
The proposed project PJM-AF1-302 is a 42 MW solar generation project located in Jefferson County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 30, 2019. The proposed commercial operation date is December 31, 2027. The project's interconnection agreement has been executed.
The proposed project is located within the PENELEC utility territory. It consists of 42 MW of solar photovoltaic generation. The point of interconnection is the Brookville-Squab Hollow 138 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Jefferson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Brookville-Squab Hollow 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF1-302