PJM-AF1-331
20 MW generation in Ogle, IL · In queue since September 2019 · Proposed COD May 2028
20 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-27
PJM-AF1-331 is a proposed 20 MW solar generation project located in Ogle County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 30, 2019. The proposed commercial operation date is May 27, 2028. The project's interconnection status is currently in the System Impact Study phase.
The proposed project is located within the ComEd utility territory. The project consists of 20 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
IL
County
Ogle
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Twombley Road
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF1-331