PJM-AF2-010
77 MW generation in Erie, PA · In queue since October 2019 · Proposed COD December 2022
77 MW
Capacity
1
Components
Solar
6y 7m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3y 2m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-15
The proposed project PJM-AF2-010 is a 77 MW solar generation project located in Erie County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on October 11, 2019. The proposed commercial operation date is December 15, 2022.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Union City-Titusville 115 kV line, and the interconnecting utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Union City-Titusville 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-010