Missouri Avenue Battery Storage Project
20 MW storage in Atlantic, NJ · In queue since November 2019 · Proposed COD April 2028
20 MW
Capacity
1
Components
Battery
6y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-30
The Missouri Avenue Battery Storage Project is a proposed 20 MW battery storage project located in Atlantic County, New Jersey. The project is in the PJM interconnection queue as entry PJM-AF2-025, with a queue entry date of November 15, 2019, and a proposed commercial operation date of April 30, 2028. The interconnection utility is AEC. The project's interconnection status is currently in the Facility Study phase.
The project, which consists of 20 MW of battery capacity, is interconnected at the Ontario 69 kV point of interconnection. The project is listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
NJ
County
Atlantic
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Ontario 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 126 STAT138 KV NISALSP
- POI Substation
- Ontario Street Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Missouri Avenue Battery Storage Project