Kincaid PV
20 MW generation in Christian, IL · In queue since October 2019 · Proposed COD December 2028
20 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-09
The Kincaid PV project is a proposed 20 MW solar generation project located in Christian County, Illinois. The project is interconnected to the ComEd utility and participates in the PJM Interconnection queue as entry PJM-AF2-032, with a queue entry date of October 28, 2019. The proposed commercial operation date is December 9, 2028, and the project has an Interconnection Agreement (IA) executed.
The project consists of 20 MW of solar photovoltaic generation. The point of interconnection is the Kincaid 345 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Christian
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Kincaid 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 21 KINCA20 KV KN-1
- POI Substation
- Kincaid Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Kincaid PV