PJM-AF2-035
72 MW generation in Hanover, VA · In queue since November 2019 · Proposed COD October 2023
72 MW
Capacity
1
Components
Solar
6y 6m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 11m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-27
PJM-AF2-035 is a proposed solar generation project located in Hanover County, Virginia. The project, with a total capacity of 72 MW, is being developed within the PJM Interconnection queue. The queue entry date for the project was November 27, 2019, with a proposed commercial operation date of October 27, 2023. Dominion is the utility associated with the project, and its interconnection status is currently in the System Impact Study phase.
The project consists of 72 MW of solar photovoltaic generation. The point of interconnection (POI) is the St. Johns 115 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Hanover
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
St. Johns 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- St. Johns Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.