PJM-AF2-041
300 MW generation in Lee, IL · In queue since December 2019 · Proposed COD November 2023
300 MW
Capacity
1
Components
Solar
6y 5m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 11m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
PJM-AF2-041 is a proposed solar generation project with a total capacity of 300 MW, located in Lee County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on December 9, 2019. Its proposed commercial operation date is November 1, 2023. The project's interconnection status is currently in the System Impact Study phase.
The proposed project is located within the ComEd utility territory. The point of interconnection is the Nelson-Electric Junction 345 kV.
Generated from interconnection queue and public data sources
State
IL
County
Lee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Nelson-Electric Junction 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-041