PJM-AF2-042
500 MW generation in Halifax, VA · In queue since December 2019 · Proposed COD December 2022
500 MW
Capacity
1
Components
Solar
6y 5m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3 years
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
PJM-AF2-042 is a proposed 500 MW solar generation project located in Halifax County, Virginia. The project is in the PJM interconnection queue as of December 9, 2019, with a proposed commercial operation date of December 31, 2022. Dominion is the interconnecting utility.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Clover-Rawlings 500 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Clover-Rawlings 500 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.