PJM-AF2-050
50 MW generation in Cambria, PA · In queue since December 2019 · Proposed COD September 2021
50 MW
Capacity
1
Components
Solar
6y 5m
In Queue
System Impact Study
IA Status
COD target: 2021
Total Duration
1y 9m
Schedule
57 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-09-01
PJM-AF2-050 is a proposed solar generation project with a total capacity of 50 MW, located in Cambria County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on December 23, 2019. The proposed commercial operation date is September 1, 2021. The interconnecting utility is PENELEC. The project's interconnection status is currently in the System Impact Study phase.
The development project consists of 50 MW of solar photovoltaic generation. The point of interconnection is the Bearrock-Johnstown 230 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Cambria
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Bearrock-Johnstown 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-050