PJM-AF2-088
6.5 MW generation in Clearfield, PA · In queue since February 2020 · Proposed COD September 2026
6.5 MW
Capacity
1
Components
Solar
6y 3m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
PJM-AF2-088 is a proposed solar generation project with a total capacity of 6.5 MW. The project is located in Clearfield County, Pennsylvania, within the PJM Interconnection region. The project, interconnecting to PENELEC, entered the PJM queue on February 5, 2020, and has a proposed commercial operation date of September 1, 2026. Its interconnection status is currently in the System Impact Study phase.
The proposed point of interconnection (POI) is the Shawville-Clearfield 34.5 kV II substation. The project consists of 6.5 MW of solar photovoltaic generation. The developer is not specified in the queue data, and there is no indication of an existing operating plant match or recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Shawville-Clearfield 34.5 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-088