Gibson Solar I
34 MW generation in King George, VA · In queue since February 2020 · Proposed COD December 2027
34 MW
Capacity
1
Components
Solar
6y 3m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-31
Gibson Solar I is a proposed 34 MW solar generation project located in King George County, Virginia. The project is being developed within the Dominion service area and has an interconnection agreement executed. It is listed in the PJM interconnection queue as entry AF2-091, with a queue entry date of February 7, 2020, and a proposed commercial operation date of December 31, 2027.
The project consists of 34 MW of solar photovoltaic generation. It is interconnected to the PJM grid at the Oak Grove-Dahlgren 230 kV point of interconnection. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
VA
County
King George
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Oak Grove-Dahlgren 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Gibson Solar I