PJM-AF2-106
150 MW generation in Pulaski, VA · In queue since January 2020 · Proposed COD February 2028
150 MW
Capacity
1
Components
Solar
6y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-28
PJM-AF2-106 is a proposed solar generation project located in Pulaski County, Virginia, within the PJM Interconnection region. The development project, with a total capacity of 150 MW, consists entirely of solar photovoltaic technology. The project is listed in the PJM interconnection queue as of January 31, 2020, with a proposed commercial operation date of February 28, 2028.
The interconnection utility is AEP, and the project's point of interconnection (POI) is the Hazel Hollow-Glen Lyn #1 138 kV line. The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
VA
County
Pulaski
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Hazel Hollow-Glen Lyn #1 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.