PJM-AF2-115
25 MW generation in Amelia, VA · In queue since February 2020 · Proposed COD December 2022
25 MW
Capacity
1
Components
Solar
6y 3m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
2y 10m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
PJM-AF2-115 is a proposed solar generation project located in Amelia County, Virginia, within the Dominion service area. The project, with a total capacity of 25 MW, consists entirely of solar photovoltaic generation. It is currently listed as active in the PJM interconnection queue, with an entry date of February 28, 2020.
The proposed commercial operation date for PJM-AF2-115 is December 1, 2022. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Jetersville-Ponton 115 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Amelia
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Jetersville-Ponton 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.