PJM-AF2-120
62 MW generation in Richmond, VA · In queue since February 2020 · Proposed COD December 2023
62 MW
Capacity
1
Components
Solar
6y 3m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 10m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
PJM-AF2-120 is a proposed solar generation project with a total capacity of 62 MW. The project is located in Richmond County, Virginia, and is being developed within the Dominion service area. It entered the PJM interconnection queue on February 28, 2020, and has a proposed commercial operation date of December 1, 2023.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Garner-Northern Neck 115 kV line. The project has appeared in recent news coverage regarding renewable energy development in the PJM region.
Generated from interconnection queue and public data sources
State
VA
County
Richmond
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Garner-Northern Neck 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.