Union Ridge Solar
107.7 MW generation in Licking, OH · In queue since February 2020 · Proposed COD January 2026
107.7 MW
Capacity
1
Components
Solar
6y 3m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
5y 11m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-01-31
Union Ridge Solar is a proposed solar generation project with a total capacity of 107.7 MW, located in Licking County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF2-122, with a queue entry date of February 29, 2020, and a proposed commercial operation date of January 31, 2026. The interconnection agreement (IA) has been executed. The interconnecting utility is AEP.
The Union Ridge Solar project has been the subject of recent news coverage, with six articles appearing in industry, deals, and regulatory publications.
Generated from interconnection queue and public data sources
State
OH
County
Licking
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Kirk 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KIRK 34.5 KV UNIONRSP
- POI Substation
- Kirk Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26