PJM-AF2-126
12 MW generation in Wood, OH · In queue since February 2020 · Proposed COD December 2021
12 MW
Capacity
1
Components
Solar
6y 3m
In Queue
System Impact Study
IA Status
COD target: 2021
Total Duration
1y 10m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
PJM-AF2-126 is a proposed solar generation project located in Wood County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 12 MW, consists entirely of solar photovoltaic technology. The queue entry date for PJM-AF2-126 is February 28, 2020, with a proposed commercial operation date of December 31, 2021. The interconnection utility is ATSI.
Currently, the project's interconnection status is in the System Impact Study phase. The point of interconnection is the Weston 69 kV II substation. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
OH
County
Wood
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Weston 69 kV II
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WESTON 138 KV T2
- POI Substation
- Weston Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-126