Frasier Solar (PJM-AF2-149) — Project Summary

Queue ID
PJM-AF2-149
Capacity
80 MW
Technology
Solar
Status
active
Location
Knox, OH
Region
PJM
Developer
IA Status
IA Executed

Frasier Solar

PJM-AF2-149BetaActiveSolarPJMLBNL + Live

80 MW generation in Knox, OH · In queue since March 2020 · Proposed COD January 2028

80 MW

Capacity

1

Components

Solar

6y 2m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection

Total Duration

7y 10m

Construction75%
Queue EntryMar 12, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-01-31

About

The proposed Frasier Solar project is an 80 MW solar generation facility located in Knox County, Ohio. The project, developed under the utility AEP, is currently active in the PJM interconnection queue as entry PJM-AF2-149, with a queue entry date of March 12, 2020. The proposed commercial operation date is January 31, 2028, and the project has an Interconnection Agreement (IA) executed.

The Frasier Solar project has been the subject of recent news coverage, with five articles categorized as regulatory matters.

Generated from interconnection queue and public data sources

Project Details

State

OH

County

Knox

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Sharp Road 69 kV

Data Source

LBNL + Live

ApplicantOpen Road Renewables±Richland Source · 2025-07-30
AgencyOhio Power Siting BoardRichland Source · 2025-07-30
RulingApprovalRichland Source · 2025-07-30
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.