PJM-AF2-177
200 MW generation in Blackford, IN · In queue since March 2020 · Proposed COD October 2023
200 MW
Capacity
1
Components
Wind
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 7m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
PJM-AF2-177 is a proposed 200 MW wind generation project located in Blackford County, Indiana. The project, which consists of 200 MW of wind capacity, is in the PJM interconnection queue as of March 20, 2020, with a proposed commercial operation date of October 31, 2023. The interconnecting utility is AEP. Its interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Sorenson-DeSoto #2 345 kV line.
The development project is sponsored within the PJM Interconnection by an unlisted developer. The project is listed as active within the queue.
Generated from interconnection queue and public data sources
State
IN
County
Blackford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Sorenson-DeSoto #2 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-177