Barbertown Solar
7 MW generation in Hunterdon, NJ · In queue since March 2020 · Proposed COD June 2026
7 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-06-30
Barbertown Solar is a proposed 7 MW solar generation project located in Hunterdon County, New Jersey. The project is in the PJM interconnection queue as entry PJM-AF2-192, with a queue entry date of March 23, 2020, and a proposed commercial operation date of June 30, 2026. The project's interconnection agreement has been executed, but its current status is listed as suspended.
The proposed project is to be interconnected with Jersey Central Power & Light (JCPL) at the Frenchtown Solar-West Flemington 34.5 kV point of interconnection.
Generated from interconnection queue and public data sources
State
NJ
County
Hunterdon
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Frenchtown Solar-West Flemington 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Barbertown Solar