PJM-AF2-199
100 MW generation in Lee, IL · In queue since March 2020 · Proposed COD November 2023
100 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 8m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
PJM-AF2-199 is a proposed solar generation project with a total capacity of 100 MW, located in Lee County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 24, 2020. Its proposed commercial operation date is November 1, 2023.
The interconnection status of the project is currently in the System Impact Study phase. The proposed point of interconnection (POI) is the Nelson-Electric Junction 345 kV. The utility is ComEd.
Generated from interconnection queue and public data sources
State
IL
County
Lee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Nelson-Electric Junction 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-199