Project PJM-AF2-200 — Project Summary

Queue ID
PJM-AF2-200
Capacity
200 MW
Technology
Solar
Status
active
Location
Lee, IL
Region
PJM
Developer
IA Status
System Impact Study

PJM-AF2-200

PJM-AF2-200BetaActiveSolarPJMLBNL

200 MW generation in Lee, IL · In queue since March 2020 · Proposed COD November 2023

200 MW

Capacity

1

Components

Solar

6y 2m

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection

Total Duration

3y 8m

Schedule

30 months past proposed COD

Impact Study25%
Queue EntryMar 24, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-11-01

About

PJM-AF2-200 is a proposed solar generation project with a total capacity of 200 MW, located in Lee County, Illinois. The project is in the PJM interconnection queue as of March 24, 2020, with a proposed commercial operation date of November 1, 2023. The interconnecting utility is ComEd.

The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Nelson-Electric Junction 345 kV.

Generated from interconnection queue and public data sources

Project Details

State

IL

County

Lee

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

ComEd

Entity

PJM

Service Type

Point of Interconnection

Nelson-Electric Junction 345 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
N ILLINOIS HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AF2-200