Stony Creek Solar
15 MW generation in Somerset, PA · In queue since March 2020 · Proposed COD October 2025
15 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
The Stony Creek Solar project is a proposed 15 MW solar generation project located in Somerset County, Pennsylvania. The project, developed under the PENELEC utility, is interconnected within the PJM Interconnection queue as entry PJM-AF2-221, with a queue entry date of March 25, 2020. The proposed commercial operation date is October 1, 2025. Its interconnection status is currently in the System Impact Study phase.
The project is linked to the existing Stony Creek Solar operating plant (EIA ID 67879). Recent news coverage has discussed the development project. The project's status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Scalp Level 22.9 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PENELEC
- POI Substation
- Scalp Level Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Stony Creek Solar