PJM-AF2-225
150 MW generation in Mclean, IL · In queue since March 2020 · Proposed COD October 2022
150 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
2y 7m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-31
PJM-AF2-225 is a proposed solar generation project with a total capacity of 150 MW, located in McLean County, Illinois. The project is in the PJM interconnection queue, having entered on March 26, 2020. The proposed commercial operation date is October 31, 2022.
The interconnection status for PJM-AF2-225 is currently in the System Impact Study phase. The interconnecting utility is ComEd, and the point of interconnection is the McLean 345 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Mclean
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
McLean 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TYSONS 230 KV SR1
- POI Substation
- TPSS#3 - McLean
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-225