PJM-AF2-226
50 MW storage in Lasalle, IL · In queue since March 2020 · Proposed COD October 2023
50 MW
Capacity
1
Components
Battery
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 7m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
PJM-AF2-226 is a proposed 50 MW battery storage project located in Lasalle County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 26, 2020. The proposed commercial operation date is October 31, 2023. The project's interconnection status is currently in the System Impact Study phase.
The project, which will connect to the ComEd utility grid at the Katydid Road 345 kV point of interconnection, consists solely of battery storage with a total capacity of 50 MW. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
IL
County
Lasalle
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Katydid Road 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-226