Washington East Solar
20 MW hybrid in Snyder, PA · In queue since March 2020 · Proposed COD December 2026
20 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-12-30
The Washington East Solar project is a proposed 20 MW hybrid solar and battery energy storage project in Snyder County, Pennsylvania. The project consists of 20 MW of solar generation. It is located within the PJM Interconnection region and is interconnected to the PPL utility via the Penns-Richfield Tie #1 69 kV.
The project, identified as queue ID PJM-AF2-233, entered the PJM queue on March 26, 2020, with a proposed commercial operation date of December 30, 2026. The project's interconnection agreement has been executed. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Snyder
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Penns-Richfield Tie #1 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Washington East Solar