Washington West Solar (PJM-AF2-234) — Project Summary

Queue ID
PJM-AF2-234
Capacity
40 MW
Technology
Solar+Battery
Status
active
Location
Snyder, PA
Region
PJM
Developer
IA Status
IA Executed

Washington West Solar

PJM-AF2-234BetaActiveSolarBatteryPJMLBNL + Live

40 MW hybrid in Snyder, PA · In queue since March 2020 · Proposed COD December 2026

40 MW

Capacity

1

Components

Solar

6y 2m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection

Total Duration

6y 9m

Construction75%
Queue EntryMar 26, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-30

About

The Washington West Solar project is a proposed 40 MW hybrid solar and battery energy storage project in Snyder County, Pennsylvania. The project, located within the PJM Interconnection region and connected to the PPL utility, consists of a 40 MW solar component.

The project is listed in the PJM interconnection queue as entry AF2-234, with a queue entry date of March 26, 2020, and a proposed commercial operation date of December 30, 2026. The project's interconnection agreement has been executed. The point of interconnection is the Sunbury Yard #1-Richfield Tie #2 69 kV line. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

PA

County

Snyder

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

PPL

Entity

PJM

Service Type

Point of Interconnection

Sunbury Yard #1-Richfield Tie #2 69 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
SUNBURY 12 KV CT 1-2

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Washington West Solar