New Haven Solar
100 MW generation in Mason, WV · In queue since March 2020 · Proposed COD January 2028
100 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-01-31
The New Haven Solar project is a proposed 100 MW solar generation facility in Mason County, West Virginia. The project is located within the PJM Interconnection region and is being developed by AEP. It consists of 100 MW of solar photovoltaic generation.
The project entered the PJM interconnection queue as entry AF2-291 on March 28, 2020. Its proposed commercial operation date is January 31, 2028, and the project has an executed Interconnection Agreement (IA). The point of interconnection is the Sporn South-Leon 138 kV line.
Generated from interconnection queue and public data sources
State
WV
County
Mason
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Sporn South-Leon 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about New Haven Solar