PJM-AF2-297
80 MW generation in Halifax, VA · In queue since March 2020 · Proposed COD March 2022
80 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
2 years
Schedule
50 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-03-12
PJM-AF2-297 is a proposed solar generation project located in Halifax County, Virginia. The project, with a total capacity of 80 MW, is in the PJM interconnection queue as of March 28, 2020. Dominion is the interconnecting utility.
The project's proposed commercial operation date is March 12, 2022. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Sedge Hill 115 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Sedge Hill 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SINAI 13 KV TX2_LOAD
- POI Substation
- Sedge Hill Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-297