Project PJM-AF2-304 — Project Summary

Queue ID
PJM-AF2-304
Capacity
89 MW
Technology
Solar+Battery
Status
active
Location
Surry, VA
Region
PJM
Developer
IA Status
Facility Study

PJM-AF2-304

PJM-AF2-304BetaActiveSolarBatteryPJMLBNL + Live

89 MW hybrid in Surry, VA · In queue since March 2020 · Proposed COD September 2028

89 MW

Capacity

1

Components

Solar

6y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

8y 6m

Facilities Study50%
Queue EntryMar 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

About

PJM-AF2-304 is a proposed 89 MW hybrid solar and battery project located in Surry County, Virginia. The project, which consists of 89 MW of solar generation, is in the PJM interconnection queue as of March 30, 2020, with a proposed commercial operation date of September 1, 2028. Dominion is the interconnecting utility.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Surry-Hopewell 230 kV line.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Surry

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Surry-Hopewell 230 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AF2-304