Deep Lake Solar
150 MW generation in Nicholas, WV · In queue since March 2020 · Proposed COD February 2029
150 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-28
Deep Lake Solar is a proposed 150 MW solar generation project located in Nicholas County, West Virginia. The project is in the PJM interconnection queue as entry PJM-AF2-316, with a queue entry date of March 30, 2020, and a proposed commercial operation date of February 28, 2029. The interconnection agreement for the project has been executed.
The project, which interconnects at the Gilboa-Jones Branch 138 kV II substation, is being developed within the APS utility territory. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
WV
County
Nicholas
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Gilboa-Jones Branch 138 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Branch
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.