PJM-AF2-349
300 MW generation in Mchenry, IL · In queue since March 2020 · Proposed COD December 2023
300 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 9m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
PJM-AF2-349 is a proposed 300 MW solar generation project located in McHenry County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2020. Its proposed commercial operation date is December 1, 2023.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the SILVER LAKE- CHERRY VALLEY 345 KV line. The project is within the ComEd utility territory.
Generated from interconnection queue and public data sources
State
IL
County
Mchenry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
SILVER LAKE- CHERRY VALLEY 345 KV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- VALLEY4 230 KV SR_1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-349