PJM-AF2-358
100 MW generation in Dorchester, MD · In queue since March 2020 · Proposed COD December 2023
100 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
3y 9m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-15
PJM-AF2-358 is a proposed solar generation project with a total capacity of 100 MW, located in Dorchester County, Maryland. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2020. The proposed commercial operation date is December 15, 2023.
The project's interconnection status is currently in the System Impact Study phase. The interconnecting utility is Delmarva Power & Light (DPL), and the point of interconnection (POI) is the Airey-Vienna 69 kV line.
Generated from interconnection queue and public data sources
State
MD
County
Dorchester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Airey-Vienna 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF2-358