Red Maple Solar
94.9 MW generation in Adams, IL · In queue since March 2020 · Proposed COD February 2028
94.9 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-02-07
Red Maple Solar is a proposed 94.9 MW solar generation project located in Adams County, Illinois. The project is in the PJM interconnection queue as entry PJM-AF2-366, with a queue entry date of March 31, 2020, and a proposed commercial operation date of February 7, 2028. The interconnecting utility is ComEd.
The project's interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
IL
County
Adams
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Crego Rd 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.